Add clear plastic roof (removable) over porch on existing/approved tent platform (sleeping tent).
Location
Spring Camp Work Camp, approximately 8.5 miles up the Unuk River.
Project timeline
1
Scoping Start
01/12/2015
2
Decision
01/2015 (Estimated)
3
Implementation
03/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Memo-ADF&G Fisheries Research Unuk River SUP Amendment #2 | Decision Signed Date: 01/23/2015 |
| Forests | Tongass National Forest |
| Districts | Ketchikan Misty Fjords Ranger District |
| Legal Land Description | CRM, T. 66 S., R. 93 E., sec. 12 |