Remove and replace culverts at four locations on Forest Highway 10 east of Yakutat to facilitate fish passage.
Location
Culverts at mileposts 8.165, 18.733, 21.426, and 24.102 along FH10.
Project timeline
1
Scoping Start
07/26/2016
2
Decision
07/2016 (Estimated)
3
Implementation
07/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Road Improvements/Construction |
| Forest Highway 10 Fish Passage Improvement | Decision Signed Date: 07/29/2016 |
| Forests | Tongass National Forest |
| Districts | Yakutat Ranger District |
| Legal Land Description | Not Applicable |