The intent of this project is to restore fish and wildlife habitat from land-disturbing activities and management of previously harvested timber units in the Nakwasina Watershed.
Location
Nakwasina watershed appx. 15 mi. north of the community of Sitka
Project timeline
1
Scoping Start
12/15/2017
2
Comment Period
03/09/2018
3
Objection Period Start
03/09/2018
4
Decision
06/2018 (Estimated)
5
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Watershed Improvements |
| Nakwasina Integrated Resource Project | Decision Signed Date: 06/13/2018 |
| Forests | Tongass National Forest |
| Districts | Sitka Ranger District |
| Legal Land Description | Not Applicable |