The project will bring an existing 5280-foot 4%u201D water transmission pipeline under permit for Paul Johnson. The waterline serves as a domestic water source for the private land owners, for fire suppression, and to generate power.
Location
Gull Cove, Idaho Inlet, Chichagof Island
Project timeline
1
Scoping Start
04/01/2018
2
Decision
05/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Paul Johnson water transmission pipeline | Decision Signed Date: 05/18/2018 |
| Forests | Tongass National Forest |
| Districts | Hoonah Ranger District |
| Legal Land Description | Gull Cove, Idaho Inlet - Hoonah Ranger District. SE1/2, Sec. 19, NW1/4, NW1/4, Sec. 29, NE1/4, NE1/4, Sec. 30, T. 42S., R.57E., Copper River Meridian |