The US Navy Back Island Permit Renewal Project proposes to renew Special Use permit KET 000901, which allows the US Navy to occupy and operate an acoustic measurement facility.
Location
T 73S R90E S17 C.R.M
Project timeline
1
Scoping Start
06/05/2018
2
Decision
09/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Back Island Permit Renewal Project | Decision Signed Date: 09/13/2018 |
| Forests | Tongass National Forest |
| Districts | Ketchikan Misty Fjords Ranger District |
| Legal Land Description | Not Applicable |