Propose to reissue special use authorization at Federal Aviation Administration's communications facility at Level Island for 20 years. Use has been authorized since 1964.
Location
Big Level Island
Project timeline
1
Scoping Start
07/19/2018
2
Decision
11/2018 (Estimated)
3
Implementation
01/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Authorize FAA Continued Use of Level Island Communication Site | Decision Signed Date: 11/15/2018 |
| Forests | Tongass National Forest |
| Districts | Petersburg Ranger District |
| Legal Land Description | Not Applicable |