On Mitkof Island, AP&T Wireless Inc proposes to install a powerline and fiber optic cable along the ground from the Crystal Mtn Comm Site to the switch yard at the Crystal Lk powerhouse. The powerline and cable would cross about 9,500' of NFS land.
Location
Crystal Mountain, Mitkof Island
Project timeline
1
Scoping Start
08/26/2019
2
Decision
01/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Crystal Mountain Communications Site Powerline and Fiber Optic Cable | Decision Signed Date: 01/19/2024 |
| Forests | Tongass National Forest |
| Districts | Petersburg Ranger District |
| Legal Land Description | Sections 12 and 13, T. 61 S., R. 80 E., Copper River Meridian |