Continue authorizing mountain top communication use on National Forest System land for the next 30 years (CY 2022-2051). No changes to the existing communication use and the support facilities are expected.
Location
SEAPA communication site is on an unnamed peak on Etolin Island.
Project timeline
1
Scoping Start
03/25/2021
2
Decision
02/2022 (Estimated)
3
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Continuation of SEAPA Etolin-Burnett Communication Use Lease | Decision Signed Date: 02/15/2022 |
| Forests | Tongass National Forest |
| Districts | Wrangell Ranger District |
| Legal Land Description | Comm site is in NE 1/4 of NW 1/4, Section 22, T. 66 S., R. 84 E., Copper River Meridian, at approximately Latitude 56 8'10.6" North, Longitude 132 24' 17.7" West |