Authorize a Special Use Permit to install and maintain approximately 6,000 feet of waterline to serve a private residence in Gull Cove near the mouth of Idaho Inlet, Chichagof Island, Alaska.
Location
Gull Cove, Idaho Inlet, Chichagof Island, Alaska
Project timeline
1
Scoping Start
06/08/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Montgomery - Gull Cove Water Transmission Pipeline Permit | Decision Signed Date: 06/08/2022 |
| Forests | Tongass National Forest |
| Districts | Hoonah Ranger District |
| Legal Land Description | Not Applicable |