Applicant is proposing a 900-foot extension of four-inch diameter high-density polyethylene above ground water transmission pipeline on National Forest System lands to serve private property at Gull Cove, Idaho Inlet.
Location
Gull Cove, Idaho inlet, Chichagof Island
Project timeline
1
Scoping Start
12/02/2024
2
Decision
03/2025 (Estimated)
3
Implementation
03/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Gull Cove Waterline Extension | Decision Signed Date: 03/13/2025 |
| Forests | Tongass National Forest |
| Districts | Hoonah Ranger District |
| Legal Land Description | T. 42 S., R. 57 E., sec 19, and T. 42 S., R. 57 E., sec 29 thru 30 Copper River Meridian |