Environmental Impact Statement · Bridger-Teton National Forest All Units · updated 5/11/2026
Dell Creek feedground:about 4 miles east on Dell Creek Road (FS Rd 30600) from Hwy 191/189, in Bondurant. Forest Park: 33 miles south on Greys River Road (FS Rd 10138) from Alpine, Wyoming. · Lincoln; Sublette, Wyoming
Wyoming Game & Fish Commission requested continued use of the Dell Creek and Forest Park feedgrounds for their long-term winter elk feeding activities. Elk are fed hay between mid-Nov thru April.
Special use management
NOI in Federal Register
01/14/2022
DEIS NOA in Federal Register
12/01/2023
FEIS NOA in Federal Register
08/01/2025
Objection Period Start
08/02/2025
Decision
04/2026 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Big Piney Ranger District; Greys River Ranger District |
| Legal Land Description | Dell Creek: N 1/2 and SW 1/4 of Sec 14, T33N, R113W. Forest Park: NW1/4 and SW1/4 of Sec 21, NW1/4 and NE1/4 of Sec 28, T33N, R116W, 6th Meridian |
Categorical Exclusion · Jackson Ranger District · updated 4/27/2026
Camp Creek Road FS Road No. 30461, north side of Highway 191, Section 32, T. 38 N., R. 115 W. · Teton, Wyoming
Wyoming Game and Fish need access to Camp Creek Road during seasonal closure to access Elk Feedground. Gate will remain closed with signage. Snow plowing as needed. Sisters of Reparation own a private inholding off Camp Creek Road. Year around access and light maintenance/add drainage if needed.
Special use management
NEPA Start Date
10/1/2025
Finding/Decision Date
4/24/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 4/24/2026 |
Categorical Exclusion · Jackson Ranger District · updated 4/27/2026
Crystal Creek road No. 30377, Sections 16 and 21, T. 42 N., R. 113 W. · Teton, Wyoming
The Red Rock Ranch is requesting a permit for current signs and egress/ingress to their property. They must drive from Gros Ventre Road to Crystal Creek Road, then take a right to get to their private home or main ranch property. There are signs along the road directing guests and a wooden archway.
Special use management
NEPA Start Date
12/19/2025
Finding/Decision Date
4/24/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-28d-USFS |
| Decision Signed Date | 4/24/2026 |
Decision Memo · Bridger-Teton National Forest All Units · updated 4/17/2026
FS Road No. 31000 (Fall Creek Road), 30995 (North Fork Fall Creek Road), 30997 (Laughry Road), 31030 (Cottonwood Work Center housing loop), US Highway 89/26 · Teton, Wyoming
Silver Star Telephone Company and Lower Valley Energy is proposing to place a new fiber optic telecommunication cable and power cable and appurtenances to upgrade facilities within and along numerous roads within the Fall Creek area.
Special use management
Decision
04/2026 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | Ntia_C(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |
Categorical Exclusion · Bridger-Teton National Forest · updated 4/1/2026
North Fork of Fall Creek Road, National Forest System (NFS) RD #30995, within Township 39 North, Range 117 West, Section 7. 43.371471, -110.915664 · Teton, Wyoming
The BTNF is planning to enhance watershed and fisheries values that are currently impaired by the unmaintained legacy road infrastructure within North Fork of Fall Creek drainage. This project entails restoring native fish passage by removing a perched culvert while improving wilderness character.
Watershed managementWildlife, fish, rare plants
Finding/Decision Date
3/20/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-40d-USFS |
| Decision Signed Date | 3/20/2026 |
Categorical Exclusion · Pinedale Ranger District · updated 3/30/2026
N 42° 59.840, W 109° 44.682, T33N R109W Section 35 · Sublette, Wyoming
The Forest Service radio repeater on Elkhart Peak is outdated and needs to be replaced with modern radio technology. The proposal to install new infrastructure, which will ensure that the facility is consistent with radio communication direction in FSM 6640 - Telecommunications.
Facility management
Finding/Decision Date
3/30/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-43d-USFS |
| Decision Signed Date | 3/30/2026 |
Categorical Exclusion · Jackson Ranger District · updated 3/5/2026
FS road 30410 (Cottonwood Creek Road), across Fish Creek to Trail Creek. T42N, R112W, Section 33 on the Jackson Ranger District. 43.56272 N, 110.18046 W. · Teton, Wyoming
This project proposes to build Beaver Dam Analogues and post assisted log structures within Trail Creek. These structures act as a sink that mimics beaver dams to bolster riparian vegetation, increase groundwater infiltration, and sequester fine sediment and ash from traveling further downstream.
Watershed managementWildlife, fish, rare plants
Finding/Decision Date
3/2/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-34d-USFS |
| Decision Signed Date | 3/2/2026 |
Environmental Impact Statement · Bridger-Teton National Forest All Units · updated 1/29/2026
The Bridger-Teton National Forest, within the Wyoming counties of Lincoln, Sublette, Teton, Fremont and Park. · Fremont; Lincoln; Park; Sublette; Teton, Wyoming
The first phase of forest planning includes preparation of an Assessment that outlines existing conditions and trends affecting the forest. This is not a decision document but public comment will be sought when the Draft Assessment is published.
Land management planning
NOI in Federal Register
05/2027 (Estimated)
DEIS NOA in Federal Register
05/2027 (Estimated)
FEIS NOA in Federal Register
05/2028 (Estimated)
Objection Period Start
05/2028 (Estimated)
Decision
09/2028 (Estimated)
Implementation
09/2028 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Creation/Revision |
| Forests | Bridger-Teton National Forest |
| Districts | Bridger-Teton National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Pinedale Ranger District · updated 12/1/2025
Union Pass area north of Pinedale and south of Dubois, WY. · Sublette, Wyoming
Commercial timber harvests in a suite of silvicultural treatments using mechanized equipment; salvage, pre- and non-commercial thinning to improve stand condition, whitebark pine restoration, and replacement of a culvert. Reassess proposal post fire.
Forest productsVegetation management (other than forest products)Fuels managementWatershed management
Decision
12/2025 (Estimated)
Implementation
05/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (18), 36 Cfr 220.6(E)(18); 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage); Watershed Improvements |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Jackson Ranger District · updated 11/25/2025
The trails included in the project are near Jackson, WY, around Teton Pass, Horse Creek Trail area in the Gros Ventre, Munger Mountain, Shadow Mountain, Swinging Bridge, and Hoback. · Teton, Wyoming
Proposed action is to allow Class 1 e-bikes on existing trails around Teton Pass and extend e-bikes seasonal restrictions at certain locations. Alt 1 would allow all 3 classes of e-bikes and includes trail construction. Draft EA comment closed 2/24.
Recreation management
Comment Period
01/24/2025
Objection Period Start
06/2025 (Estimated)
Decision
10/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
Decision Memo · Pinedale Ranger District · updated 9/22/2025
Located approximately 25 miles north of Pinedale and 10 miles east of Bondurant, near Highway 189/191, in Sublette County, WY. · Sublette, Wyoming
The District proposes to reduce fuels, improve forest health and create favorable conditions for managing wildfire on 3,000 acres in a wildland-urban interface. Treatments include mechanical harvest, thinning, Rx fire and planting. Comment by 1/6/25.
Vegetation management (other than forest products)Fuels management
Comment Period
12/18/2024
Decision
09/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (5) |
| Special Authority | Hfra Title Vi: Insect And Disease Projects |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 9/22/2025
About 20 miles northeast of Jackson, WY · Teton, Wyoming
Fuel treatments, including prescribed fire and commercial and non-commercial thinning, at Shadow Mountain to enhance aspen, open grassland, and forb communities. It would also reduce fuels within the WUI. Some prescribed fire may be in 2001 Roadless.
Wildlife, fish, rare plantsFuels management
Comment Period
04/14/2025
Decision
09/2025 (Estimated)
Implementation
04/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Species Habitat Improvements |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District; Buffalo Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Greys River Ranger District · updated 6/30/2025
Greys River District near the bottom of Forest Road 10209 (Wickiup) in Section 8, T.31N., R.118W., 06. · Lincoln, Wyoming
The Osmond Service and Improvement District (OSID) proposed to expand upon their existing water development infrastructure by constructing a 350,000-gallon water tank and replacing an existing water pipeline. Comment period open through May 1, 2025.
Special use management
Comment Period
04/16/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Greys River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 6/17/2025
About 7 miles south of Jackson, WY · Teton, Wyoming
Silver Star has been funded by a USDA rural grant to install fiber optic line along Game Creek, Porcupine Creek, Henry's Road, Horse Creek Mesa, and Horse Creek. Comment period ended 3/24/25.
Special use management
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Section 26, 34, T.40N., R.116W., Sections 2, 3, 11, 12, 14, T.39N., R.116W., 6th Principal Meridian |
Decision Memo · Bridger-Teton National Forest All Units · updated 6/17/2025
Management Area 41, Jackson Hole South, off of Fall Creek Road · Teton, Wyoming
WYDOT proposes to install a WyoLink telecommunication site near the top of Pritchard Pass to enhance communication in the Snake River Corridor and Hoback area and increase public safety.
Special use management
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Latitude 43 19' 1.81"N / Longitude 110 48' 11.81" W |
Decision Memo · Greys River Ranger District · updated 5/30/2025
T. 33N., R. 118W., portions of section 22, 27, 34, and 35. T. 32N., R. 118W., portions of section 4 and 5. Parallel to RD#10081 and Spruce Hollow · Lincoln, Wyoming
Change the grazing system of the Grover Blaney Allotment from a continuous grazing system to a 3-unit rotational grazing system.
Grazing management
Decision
05/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Allotment Management |
| Forests | Bridger-Teton National Forest |
| Districts | Greys River Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pinedale Ranger District · updated 3/31/2025
West edge of Pinedale Ranger District, including small portion of the Gros Ventre Wilderness Area. · Sublette, Wyoming
Proposal to graze cattle on 4 former sheep allotments: Elk Ridge, Lime Creek, Rock Creek, and Tosi Creek. These allotments would be grazed by currently permitted cattle in the Upper Green River Area.
Grazing managementProjects that may affect wilderness (for mailing list contacts)
Comment Period
11/24/2021
Objection Period Start
09/2025 (Estimated)
Decision
11/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pinedale Ranger District · updated 3/24/2025
Southern Wind River Range · Sublette, Wyoming
Forest Service decided to close Temple Creek and Bunion Creek allotments and proposes to reauthorize livestock grazing on Muddy Canyon Allotment. This project is currently on hold.
Grazing management
Comment Period
03/28/2015
Objection Period Start
09/2025 (Estimated)
Decision
12/2025 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Grazing, Rescissions Act Of 1995 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pinedale Ranger District · updated 3/24/2025
New Fork Lake area east of Pinedale, WY. · Sublette, Wyoming
New Fork Lake Irrigation District has proposed to rehabilitate the New Fork Lake Dam at current location to meet statewide safety requirements and increase water storage to improve the availability of legally-secured water to downstream users.
Special use management
Comment Period
03/26/2020
Objection Period Start
03/2025 (Estimated)
Decision
05/2025 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Pinedale Ranger District · updated 3/24/2025
Silver Lake Dam is within, and pre-dates, the Bridger Wilderness Area on the south slope of the Wind River Mountains, east of Boulder, WY. · Sublette, Wyoming
The Silver Lake Irrigation District has proposed to rehabilitate the dam, inside the Bridger Wilderness, that supplies the water under their state water rights. State engineers have rated the dam's hazard at high. Proposal to raise dam & outlet work.
Special use managementProjects that may affect wilderness (for mailing list contacts)
Scoping Start
05/2025 (Estimated)
Comment Period
05/2025 (Estimated)
Objection Period Start
10/2025 (Estimated)
Decision
04/2026 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 3/11/2025
Highway 22 between Wilson, WY and Victor, ID. · Teton, Wyoming
Wyoming Department of Transportation, with Federal Highway Administration, to reconstruct Hwy 22 at the Big Fill Slide. Some excess fill material may be placed on the Jackson Ranger District at the Phillips Bench parking area southeast of Hwy 22.
Road management
Decision
07/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 40 Cfr 1506.3(D) |
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | T.41N., R.118W., Sec. 23, 6th Principal Meridian |
Decision Memo · Buffalo Ranger District · updated 3/3/2025
East of Moran, WY, in Teton County. · Teton, Wyoming
Residents have requested a permit to brush out a quarter-mile historic two-track from a private subdivision inholding to Highway 287, east of Moran, for emergency use. This project is in inventoried roadless area.
Special use management
Decision
02/2025 (Estimated)
Implementation
03/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Buffalo Ranger District |
| Legal Land Description | T45N, R113W, S29 |
Decision Memo · Pinedale Ranger District · updated 12/6/2024
About 20 miles southwest of Boulder, WY in the southern portion of the Wind River Range. · Sublette, Wyoming
Treat up to 3,000 ac to improve forest health, protect infrastructure and egress within the Big Sandy wildland-urban interface area and portion of the West Slope Winds roadless area. Actions include thinning, sanitation, salvage and pile burning.
Fuels managementClimate change adaptation
Decision
12/2024 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Timber Sales (Salvage) |
| Forests | Bridger-Teton National Forest |
| Districts | Pinedale Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 10/31/2024
South of Jackson, WY off of Highway 191. · Teton, Wyoming
A reciprocal easement between the United States and Melody Ranch Investments I LLC to maintain historic public access to NFS lands between Game Creek and Wilson Canyon.
Special use management
Decision
08/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Section 27, T.40N., R.116W., 06 |
Decision Memo · Bridger-Teton National Forest All Units · updated 8/14/2024
The Big Spring day use Site is located off of the Big Spring Scenic Backway, Forest Road #10062 on the Kemmerer Ranger District. · Lincoln, Wyoming
Installation of a vault toilet at the Big Spring day use area.
Recreation management
Decision
08/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Facility Improvements/Construction |
| Big Spring Day Use Area Vault Toilet | Decision Signed Date: 08/12/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Kemmerer Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Kemmerer Ranger District · updated 8/2/2024
LaBarge Creek, eastern Kemmerer Ranger District · Lincoln, Wyoming
Proposal to study causes of poor recruitment of Colorado River cutthroat trout in La Barge Creek drainage and potential effects of disease. Sampling would be conducted for 21 days in 2025 and includes water samples for eDNA analysis.
Special use managementWildlife, fish, rare plants
Decision
07/2024 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3); 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Species Population Enhancements |
| Decision Decided Date | 07/23/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Kemmerer Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Greys River Ranger District · updated 8/2/2024
Areas burned since 1988 on the Greys River Ranger District. · Lincoln, Wyoming
Proposal for a scientific germination experiment that would include planting native seeds (Douglas-fir & lodgepole pine) in 2024 and measuring germination & establishment rates in summer of 2025, after which all planted trees will be removed.
Special use management
Decision
07/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3); 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Decision Decided Date | 07/23/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Greys River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Bridger-Teton National Forest All Units · updated 7/23/2024
Start at the Middle Piney Lake (Big Piney Ranger District) and finish on private property near the Meadow Creek Trailhead (Greys River Ranger District). · Lincoln; Sublette, Wyoming
Everlong Endurance proposes a 100-mile running race to be held on the Big Piney and Greys River Ranger Districts from August 9-11th, 2024. This race was previously held on the Bridger-Teton National Forest on similar routes in 2023, 2022 & 2021.
Special use management
Decision
07/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (12), 36 Cfr 220.6(D)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 07/23/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Big Piney Ranger District; Greys River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Buffalo Ranger District · updated 7/14/2024
SW1/4SW1/4 sec, 29, T. 45 N., R. 112 W., 6th Principal Meridian · Teton, Wyoming
The Bridger-Teton proposes to install a new radio repeater on Rosie's Ridge to replace the existing repeater. Teton County, WY would move their equipment into the new repeater.
Facility management
Decision
07/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Forests | Bridger-Teton National Forest |
| Districts | Buffalo Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 7/9/2024
The Sidewalk Trail is directly southeast of the Town of Jackson. The Parallel Trail is about 7.5 miles west of Jackson. · Teton, Wyoming
Jackson Ranger District proposes to extend the Sidewalk Trail from Cache Creek Trailhead to Forest Service boundary and reroute the Parallel Trail to the lower end of the Trail Creek Trailhead.
Recreation management
Decision
07/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Sixth principal meridian T. 41 N., R. 116 W., Sec. 35; T. 41 N., R. 117 W., Sec. 29 |
Decision Memo · Greys River Ranger District · updated 6/6/2024
Various units along Greys River Road FS10138, Little Greys River Road FS 10124 and Grover Park Road FS10081. · Lincoln, Wyoming
The district proposes various treatments to increase fuel breaks along busy roads. These treatments support fire management that is economically efficient, responsive to land management objectives and provides for public and firefighter safety.
Fuels managementVegetation management (other than forest products)
Decision
06/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Noxious Weed Treatments |
| Forests | Bridger-Teton National Forest |
| Districts | Greys River Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Jackson Ranger District · updated 6/4/2024
Gros Ventre Drainage. Head of Haystack Creek, near Bear Paw Pass. · Teton, Wyoming
To utilize prescribed burning for the regeneration of aspen stands, reinvigoration of forb communities, and the maintenance of grassland meadows in year-round habitat, winter range, and migration routes for a variety of big game species.
Wildlife, fish, rare plantsClimate change adaptation
Decision
06/2024 (Estimated)
Implementation
09/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Kemmerer Ranger District · updated 5/13/2024
Along FS Roads 10432, 10072, 10071, 10069, 10159, 10156. · Lincoln, Wyoming
The district proposes various treatments to increase fuel breaks along busy roads. These treatments support fire management that is economically efficient, responsive to land management objectives and provides for public and firefighter safety.
Vegetation management (other than forest products)Fuels management
Decision
05/2024 (Estimated)
Implementation
07/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Noxious Weed Treatments |
| Forests | Bridger-Teton National Forest |
| Districts | Kemmerer Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Jackson Ranger District · updated 4/22/2024
Adjacent to Teton Village, 8 mi northest of Jackson, WY. · Teton, Wyoming
Project proposal: replace Sublette lift; construct and modify ski runs, traverses, terrain parks, and visitor-service facilities; develop summer recreation opportunities; avalanche control infrastructure; fuels reduction.
Recreation managementSpecial use managementClimate change adaptation
Comment Period
07/01/2023
Objection Period Start
01/11/2024
Decision
04/2024 (Estimated)
Implementation
04/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Sixth principal meridian, T42N R117W Sections 13, 14, 15, 22, 23, 24 |
Decision Memo · Kemmerer Ranger District · updated 4/22/2024
East of the Dry Fork of Smiths Fork River and west of Hobble Creek Campground, near Cokeville, Wyoming. · Lincoln, Wyoming
The forest, collaborating with BLM and WGFD, proposes to broadcast burn approx. 1400 acres to reduce conifer overstory and promote Aspen suckering. Desired vegetation conditions include reduced fuel loading and improved desirable wildlife habitat.
Fuels managementVegetation management (other than forest products)
Decision
04/2024 (Estimated)
Implementation
08/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Forests | Bridger-Teton National Forest |
| Districts | Kemmerer Ranger District |
| Legal Land Description | T 28N, R118W, Sec 3,11,14,23,26,35 |
Decision Memo · Jackson Ranger District · updated 4/12/2024
Approximately 6 miles northeast of Jackson, WY between the National Elk Refuge and the Gros Ventre Wilderness. · Teton, Wyoming
The Jackson RD proposes multiple projects in the Curtis Canyon area. It includes improving the drainage and surface on NFS Rd 30445, expanding the developed campground, and relocating the Goodwin Lake trail and trailhead. Decision available.
Recreation management
Comment Period
01/31/2023
Decision
04/2024 (Estimated)
Implementation
05/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (20), 36 Cfr 220.6(E)(20); 32.2 (22), 36 Cfr 220.6(E)(22); 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Developed Site Management; Trail Management; Road Maintenance; Road Improvements/Construction |
| Curtis Canyon Projects | Decision Signed Date: 04/12/2024 |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | T41N R115W Sec. 12-17, 22-23 6th Principal Meridian |
Environmental Impact Statement · R4 - Intermountain Region All Units · updated 10/25/2023
Sagebrush lands in National Forests of Nevada, Utah, southern Idaho, southwest Montana, southwest & south-central Wyoming and northern Colorado. · Adams; Blaine; Bonneville; Camas; Caribou; Cassia; Elmore; Fremont; Madison; Churchill; Clark; Elko; Eureka; Humboldt; Lincoln; Nye; Pershing; Washoe; White Pine; Beaver; Box Elder; Cache; Carbon; Daggett; Davis; Duchesne; Emery; Garfield; Grand; Iron; Juab; Kane; Millard; Morgan; Piute; Rich; Salt Lake; San Juan; Sanpete; Sevier; Summit; Tooele; Uintah; Utah; Wasatch; Washington; Wayne; Weber; Albany; Campbell; Carbon; Converse; Crook; Laramie; Lincoln; Natrona; Niobrara; Platte; Sublette; Teton; Weston; Jackson; Moffat; Routt, Colorado; Idaho; Nevada; Utah; Wyoming
The Forest Service is considering amending its land management plans to address new and evolving issues arising since implementing sage-grouse plans in 2015. This project is in cooperation with the USDI Bureau of Land Management.
Land management planningWildlife, fish, rare plants
NOI in Federal Register
11/21/2017
DEIS NOA in Federal Register
10/05/2018
FEIS NOA in Federal Register
08/02/2019
Objection Period Start
08/02/2019
Decision
12/2020 (Estimated)
Implementation
01/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Plan Amendment |
| Forests | Medicine Bow-Routt National Forest; Ashley National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest |
| Districts | Medicine Bow-Routt National Forest All Units; Ashley National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units |
| Legal Land Description | Not Applicable |