Silver Star Telephone Company and Lower Valley Energy is proposing to place a new fiber optic telecommunication cable and power cable and appurtenances to upgrade facilities within and along numerous roads within the Fall Creek area.
Location
FS Road No. 31000 (Fall Creek Road), 30995 (North Fork Fall Creek Road), 30997 (Laughry Road), 31030 (Cottonwood Work Center housing loop), US Highway 89/26
Project timeline
1
Scoping Start
10/03/2025
2
Decision
04/2026 (Estimated)
3
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | Ntia_C(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Bridger-Teton National Forest |
| Districts | Jackson Ranger District |
| Legal Land Description | Not Applicable |