Categorical Exclusion · Shasta-Trinity National Forest · updated 6/10/2026 · decision 8/2026 (Estimated)
National Forest System lands east of the community of Trinity Center, CA and northeast of the community of Lewiston, CA. · Shasta; Trinity, California
Creation of linear fuel breaks to modify future fire behavior and connect with fuel breaks on adjacent private lands, to reduce risk of uncharacteristic wildfire and reduce risk to communities. For project documents visit: https://usfs-public.box.com/s/6a1i45z4za8fpq24158rf0mhjhresu8d
Fuels management
NEPA / regulatory detail
| Categorical Exclusion | Pub. L. 117-58, Sec. 40806 |
Environmental Assessment · Shasta-Trinity National Forest · updated 6/5/2026 · decision 2/2027 (Estimated)
The Project area is primarily within the Burnt Ranch and Big Bar high-risk firesheds. Most of the Project area is also located within the wildland urban interface of several rural communities. · Humboldt; Trinity, California
The Project designed to reduce the risks associated with high intensity wildfire and improve forest health and function through forest thinning, reduction of hazardous fuels, reforestation and prescribed fire.
Forest productsFuels managementVegetation management (other than forest products)
NEPA Start Date
2/27/2026
Project documents
Environmental Assessment · Shasta-Trinity National Forest · updated 6/4/2026 · decision 2/2027 (Estimated)
The project area is within the Weaverville Ranger District and the Trinity Unit of the National Recreation Area on the Shasta-Trinity National Forest in the vicinity of the HWY 3 corridor. · Trinity, California
The proposed project is designed to reduce risk to rural communities from catastrophic wildfire by reducing hazardous fuels, increasing safety adjacent to critical egress/ingress routes, and improving the resiliency of forested ecosystems.
Forest productsFuels managementVegetation management (other than forest products)
NEPA Start Date
2/17/2026
Project documents
Categorical Exclusion · Mt. Shasta Ranger District · updated 5/29/2026 · decision 6/2026 (Estimated)
The project is located west of the town of Castella near root and castle creeks. · Shasta; Siskiyou, California
The project is proposed to recover the economic value of fire impacted stands, reduce the risk from roadside hazards, accelerate forest recovery, and reduce the likelihood and intensity of a reburn. Project information is available at - https://usfs-public.box.com/s/al78orqta5ilowffv2snxq4ie6y0eemm
Forest productsFuels managementRegulations, directives, ordersVegetation management (other than forest products)
NEPA Start Date
12/8/2025
NEPA / regulatory detail
| Categorical Exclusion | TVA 31 (18 CFR Appendix A to Subpart C of Part 1318(31)) |
Environmental Assessment · McCloud Ranger District · updated 5/27/2026
The project is located approximately 6 miles East of McCloud, north of Highway 89, and includes the lower portions of the Pilgrim Creek and Edson Creek roads. · Siskiyou, California
The Shasta-Trinity National Forest proposed the Ash Creek Forest Health and Fuels Reduction project to address high stand densities, on-going insect and disease outbreaks, and wildfire risk. Project information is available at: https://usfs-public.box.com/s/wqgxkuomwx42lfx6f31owbqoep2w5jyi
Forest productsFuels managementVegetation management (other than forest products)
Project documents
Environmental Assessment · Weaverville Ranger District · updated 5/12/2026
From the Hayfork Divide to the Community of Junction City and north into the Canyon Creek Drainage. · Trinity, California
e Project is being designed to lower high- severity wildfire risk to the community of Junction City by reducing hazardous fuels around the community and improving forest health and resilience.
Fuels managementVegetation management (other than forest products)
Project documents
Categorical Exclusion · Shasta-Trinity National Forest · updated 5/11/2026 · decision 7/2026 (Estimated)
National Forest System lands to the north and east of Shasta Lake. · Shasta, California
Create linear fuel breaks to modify future fire behavior and connect fuel breaks on adjacent private lands, to reduce risk of uncharacteristic wildfire while also reducing risk to nearby communities. For project documents, visit: https://usfs-public.box.com/s/7oxlzaz0ebn7zb1fjs9amje8izehgqwf
Fuels management
NEPA / regulatory detail
| Categorical Exclusion | Pub. L. 117-58, Sec. 40806 |
Decision Memo · Mt. Shasta Ranger District · updated 5/6/2026
The project is in the Parks-Eddy and Upper Trinity Management Areas and is located primarily in the wildland-urban interface. Please refer to the planning area map. · Siskiyou, California
The Forest plans to create a linear fuelbreak approximately 500 feet on either side of FS 17 Road to help protect the wildland-urban interface and establish safe routes for the public and firefighters in a wildfire situation.
Fuels management
Decision
01/2026 (Estimated)
Implementation
07/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6); 32.3(11) |
| Special Authority | 2021 Infrastructure: Fuel Break Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Watershed Improvements |
| Parks-Trinity- Categorical Exclusion Review & Decision Memo | Decision Signed Date: 01/06/2026 |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Mt. Shasta Ranger District · updated 2/24/2026
The Project is along the north and northwest flanks of Mount Shasta, south of Highway 97, and north of the Mount Shasta Wilderness. Please refer to the planning area map. · Siskiyou, California
The Forest plans to improve, realign, and decommission project roads to establish a minimum and efficient transportation system and address safety, accessibility, and maintenance concerns.
Road management
Comment Period
05/23/2025
Objection Period Start
09/03/2025
Decision
10/2025 (Estimated)
Implementation
12/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Road Improvements/Construction; Travel Management |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 8/18/2025
T. 34 N., R. 6 W., Section 12. Backbone Inventoried Roadless Area. · Shasta, California
Issuance of a special use permit to authorize a private landowner to construct a new access road that would be 2,337 feet long by 30 feet wide on National Forest System lands. Road location is within the Backbone Inventoried Roadless Area.
Special use management
Decision
05/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Roadless Area Management; Road Improvements/Construction |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 8/18/2025
Lakehead, CA and surrounding area (T.35N., R.5W., Sections 12, 13, 23, 24, 26) · Shasta, California
Authorize the use and occupancy of National Forest System lands for PG&E's Antler 1101 1384 Phases 1, 1.2, 1.3 and 2 project to underground powerlines by issuing an amendment to PG&E's existing special use authorization SHF02262019 ("Master Permit").
Special use management
Decision
08/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 8/18/2025
The project is located along Statton Road, Herman Way, and Antlers Road approximately 3.4 miles southeast, 1.31 miles southeast, and 0.43 miles east of Lakehead, California · Shasta, California
Authorize the use and occupancy of NFS lands for PG&E's Antler Undergrounding 1101CB, 11011612 Phase 1.3, 11011612 Phase 1.6 project to underground powerlines by issuing an amendment to PG&E's existing special use authorization SHF02262019
Special use management
Scoping Start
08/2025 (Estimated)
Decision
09/2025 (Estimated)
Implementation
10/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Shasta Trinity National Forest All Units · updated 7/16/2025
Trinity River watershed on Forest Service managed land in Trinity County, California. Please refer to the project map for more information. · Trinity, California
The purpose of the project is to enhance quality and quantity of accessible cold-water aquatic habitat and water temperature conditions, and decrease fine sediment loading through watershed restoration activities in the Trinity River watershed.
Wildlife, fish, rare plantsWatershed managementClimate change adaptation
Comment Period
03/28/2025
Objection Period Start
05/21/2025
Decision
07/2025 (Estimated)
Implementation
04/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Species Population Enhancements; Special Area Management; Watershed Improvements |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District; Hayfork Ranger District; Big Bar Ranger District; Weaverville Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Hayfork Ranger District · updated 6/11/2025
T2N R7E Section 25 and 26 · Trinity, California
The FS will work with the Watershed Center of Hayfork, CA to restore floodplain function, raise the groundwater table, increase streamflow, decrease water temperatures, and decrease erosion and sedimentation, ultimately improving wildlife habitat.
Wildlife, fish, rare plantsVegetation management (other than forest products)
Decision
06/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Forests | Shasta Trinity National Forest |
| Districts | Hayfork Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Weaverville Ranger District · updated 6/2/2025
The Project is located within the following legal locations with reference to the Mount Diablo Base and Meridian: %u25CF Township 36 North, Range 08 West: Sections 24, 26, 3 · Trinity, California
The purpose of the Project is to increase the effectiveness of fuel breaks and fuel reduction projects across ownership boundaries, to improve forest health and function, and to improve ingress and egress for firefighters and the public.
Forest productsFuels management
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Biomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Green) |
| Forests | Shasta Trinity National Forest |
| Districts | Weaverville Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Shasta Trinity National Forest All Units · updated 5/13/2025
The entirety of both the Klamath and Shasta-Trinity National Forests excluding the Ukonom Ranger District. · Jackson; Humboldt; Modoc; Shasta; Siskiyou; Tehama; Trinity, California; Oregon
Fuels reduction and prescribed fire across the landscape. For more information, visit: https://www.fs.usda.gov/r05/klamath/projects/66583
Fuels management
Comment Period
01/2026 (Estimated)
Decision
05/2026 (Estimated)
Implementation
06/2026 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | 2021 Infrastructure: Emergency Actions |
| Notice and Comment Regulation | 2021 Infrastructure: Emergency Actions |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Trinity National Forest All Units |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 3/28/2025
Trinity Lake, Stuart Fork Arm. One mile off Highway 3 on Forest Road 35N02X. · Trinity, California
Remove existing asphalt boat ramp & replace with a two-lane, concrete, v-grooved, low-water ramp with turn-arounds & sidewalk. Add parking area above high water mark of Trinity Lake. Replace existing restroom with new restroom. Widen access driveway.
Recreation management
Scoping Start
06/2025 (Estimated)
Decision
08/2025 (Estimated)
Implementation
09/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Forests | Shasta Trinity National Forest |
| Districts | Weaverville Ranger District |
| Legal Land Description | Township 35 N., Range 8 W., Section 31 |
Decision Memo · Shasta Lake Ranger District · updated 3/28/2025
Hogback Mountain, just south of the summit and Forest Service's Hogback Fire Lookout. Section 17, T.35N., R.1W., MDM · Shasta, California
Issuance of a 30-year special use authorization to PG&E for construction, operation & maintenance of a remote microgrid on Hogback Mountain to replace the existing source of service via the existing Pit No. 7 1101 electric distribution 12KV line.
Special use management
Scoping Start
05/2025 (Estimated)
Decision
06/2025 (Estimated)
Implementation
07/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Shasta Trinity National Forest All Units · updated 3/18/2025
Project activities occur around the community of Hyampom, CA. · Trinity, California
This project proposes to reduce wildfire risk to the community of Hyampom and improve forest resiliency through forest thinning, reduction of hazardous fuels and prescribed fire to reestablish natural fire regimes.
Forest productsVegetation management (other than forest products)Fuels management
Comment Period
01/09/2025
Decision
03/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | 2021 Infrastructure: Emergency Actions |
| Notice and Comment Regulation | 2021 Infrastructure: Emergency Actions |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Special Products Sales; Roadless Area Management; Special Area Management; Timber Sales (Green) |
| Forests | Shasta Trinity National Forest |
| Districts | Hayfork Ranger District |
| Legal Land Description | T2N, R6E, Sec 1, 12-14, R7E, Sec 5-8, 17-20, 28-29, T3N, R5E, Sec 1, R6E, Sec 1-17, 19-29, 34-36, R7E, Sec 4-9, 18-23, 26-33, 35, T4N, R5E, Sec 25, 36, R6E, Sec 25, 30-33, 36, and R7E, Sec 29-32 |
Decision Memo · Shasta Trinity National Forest All Units · updated 2/27/2025
The project is located near the communities of Peanut and Wildwood, California. · Trinity, California
Up to 19-miles of motorized user created trails would be added to the system. These trails would be constructed and maintained to Forest Service standards.
Recreation management
Decision
02/2025 (Estimated)
Implementation
05/2025 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Trail Management |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District |
| Legal Land Description | T29N, R12W Sec. 1, 2, 12. T29N, R11W Sec. 2, 3, 7, 8, 9, 10, 11, 12, 13, 14, 17, 23, 24, 25, 26. T30N, R11W Sec. 4, 5, 6, 9, 10. T31N, R11W Sec. 31, 32, 33. T29N, R10W, Sec 23. |
Environmental Assessment · Mt. Shasta Ranger District · updated 1/3/2024
Approximately 3 miles west of Mount Shasta, CA, encompassing areas between the Castle Lake Road, South Fork Sacramento Road and southwest to Gumboot Lake. · Siskiyou, California
Establish fuel management zones; thin trees; reduce fuels; restore meadows; develop new/expand existing campgrounds & parking; establish trailheads & trails; & repair riparian/habitat damage.
Recreation managementVegetation management (other than forest products)Fuels management
Comment Period
07/21/2023
Decision
12/2023 (Estimated)
Implementation
12/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | 2021 Infrastructure: Emergency Actions |
| Notice and Comment Regulation | 2021 Infrastructure: Emergency Actions |
| Project Activity | Developed Site Management; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Special Use Authorizations; Trail Management; Roadless Area Management; Road Improvements/Construction; Scenery Management; Watershed Improvements |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 8/25/2023
Shasta Unit of the National Recreation Area. Shasta Lake, Sacramento Arm. Section 13, T. 34N., R. 5W. and Section 18, T. 35N., R. 4W., MDM · Shasta, California
Issuance of a new 20-year special use authorization (permit) to replace the existing permit which will allow for continued operation and management of Antlers Resort Marina. No changes will be made to currently authorized operations or facilities.
Special use management
Decision
08/2023 (Estimated)
Implementation
08/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 08/25/2023 |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Decision Memo · Shasta Lake Ranger District · updated 5/15/2023
Township 35 North, Range 5 West, Section 12 and Township 29 North, Range 10 West, Section 13 MDM · Shasta, California
Issue new special use permit to Shasta County to replace expiring permits. There will be no changes to the authorized facilities or increases in the scope or intensity of authorized activities.
Special use management
Decision
05/2023 (Estimated)
Implementation
05/2023 (Estimated)
Project documents
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (11), 36 Cfr 220.6(D)(11) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Decision Decided Date | 05/15/2023 |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District; Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |
Environmental Assessment · Yolla Bolla Ranger District · updated 3/2/2023
Beegum Creek watershed in the South Fork Management Unit of the Shasta-Trinity National Forest. · Shasta; Tehama, California
Road-related improvements, including road decommissioning and safe OHV recreation opportunities, in the Beegum Creek Watershed of the Shasta-Trinity National Forest.
Recreation managementWatershed management
Comment Period
08/2020 (Estimated)
Objection Period Start
01/2021 (Estimated)
Decision
05/2021 (Estimated)
Implementation
06/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Road Maintenance; Watershed Improvements |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District |
| Legal Land Description | The watershed is located in T.29N., R.11W., sections 24 through 26 and 35 through 36; T.28N., R.11W., sections 1, 2, and 11 through 13; T.28N., R.10W., sections 1 through 27 and 34 through 36; T.27N., |
Environmental Impact Statement · Shasta Trinity National Forest All Units · updated 1/13/2023
See project map · Trinity, California
The Trinity Public Utilities District and the Western Area Power Administration (lead Federal agency) propose a right-of-way expansion and vegetation management project to reduce fire risk to the surrounding communities. STNF is a cooperating agency.
Special use management
NOI in Federal Register
12/11/2020
DEIS NOA in Federal Register
04/2023 (Estimated)
FEIS NOA in Federal Register
12/2023 (Estimated)
Objection Period Start
10/2023 (Estimated)
Decision
12/2023 (Estimated)
Implementation
01/2024 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | 219 (2012) |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Trinity National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Assessment · Shasta Trinity National Forest All Units · updated 4/12/2021
The outfitter and guide activities occur at various locations across the Shasta-Trinity National Forest on all the management units. · Shasta; Siskiyou; Trinity, California
The Shasta-Trinity National is amending its process for authorizing outfitter and guide permits and will issue both temporary permits (authorizes use for less than one year) and priority permits (authorizes use for ten years).
Special use management
Comment Period
11/03/2020
Objection Period Start
01/27/2021
Decision
04/2021 (Estimated)
Implementation
04/2021 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Trinity National Forest All Units |
| Legal Land Description | Not Applicable |
Environmental Impact Statement · Shasta Trinity National Forest All Units · updated 8/29/2018
Immediately north and east of the community of Wildwood, California and south of Chanchelulla Wilderness. · Trinity, California
Thinning and fuels reduction to enhance and protect late successional habitat.
Wildlife, fish, rare plantsForest productsFuels managementVegetation management (other than forest products)
NOI in Federal Register
10/08/2009
DEIS NOA in Federal Register
09/10/2010
FEIS NOA in Federal Register
05/06/2011
Decision
04/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Green); Watershed Improvements |
| Gemmill Thin Project | Decision Signed Date: 04/16/2009 (Reversed in Appeal (215)) Legal Notice Date: 04/24/2009 |
| Gemmill Thin Project Record of Decision | Decision Signed Date: 04/25/2011 Legal Notice Date: 05/06/2011 |
| Forests | Shasta Trinity National Forest |
| Districts | Yolla Bolla Ranger District |
| Legal Land Description | Townships 29 and 30 North, Ranges 10 and 11 West, Mount Diablo Meridian, |