Proposal from McKenzie Electric Cooperative, Inc. to construct, operate, and maintain a new electric line on National Forest System (NFS) lands to provide safe, efficient, and reliable power sources to customers
Location
Section 29, 30 & 32 T145N R101W, 5th PM, McKenzie County, North Dakota
Project timeline
1
Scoping Start
01/26/2024
2
Decision
05/2024 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| McKenzie Electric Cooperative Inc, Roughrider Southwest New Build | Decision Signed Date: 05/22/2024 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |