To construct approximately 2,185 feet of range water pipeline and replace an existing stock tank.
Location
Section 30, T145N, R101W, 5th PM, McKenzie County, North Dakota
Project timeline
1
Scoping Start
06/06/2025
2
Decision
06/2025 (Estimated)
3
Implementation
08/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Pasture 7-3 ADP 430 Magpie Range Water Pipeline | Decision Signed Date: 06/30/2025 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |