Replace approximately 35,760 feet of existing overhead single-phase line with underground single-phase line
Location
NW Billings Co., ND
Project timeline
1
Scoping Start
06/30/2025
2
Decision
10/2025 (Estimated)
3
Implementation
12/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| McKenzie Electric Cooperative replacement electrical line | Decision Signed Date: 10/31/2025 |
| Forests | Dakota Prairie Grasslands |
| Districts | Medora Ranger District |
| Legal Land Description | T143N, R102W; T144N, R102W |