Proposal to build approximately 4,785 feet of three-phase underground electric line with a majority being along Forest System Road #821. MEC requested a 20-foot-wide easement for construction and maintenance of the project.
Location
Section 22, T147N, R101W, 5th PM, McKenzie County, North Dakota
Project timeline
1
Scoping Start
08/07/2025
2
Decision
09/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| McKenzie Electric Cooperative Inc., White Horse Intake Electric Line | Decision Signed Date: 09/11/2025 |
| Forests | Dakota Prairie Grasslands |
| Districts | Mckenzie Ranger District |
| Legal Land Description | Not Applicable |