The overall purpose is to: improve forest health; reduce potential risk to private property; maintain & improve wildlife habitat; and improve watershed conditions. Timber outputs will be used to offset treatment costs & support economic structure..
Location
T27N, R04E; T28N, R04E; R29N, 04E; (Boise Meridian)
Project timeline
1
NOI in Federal Register
02/12/2014
2
DEIS NOA in Federal Register
03/10/2023
3
FEIS NOA in Federal Register
09/08/2023
4
Objection Period Start
09/08/2023
5
Decision
12/2024 (Estimated)
6
Implementation
11/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Timber Sales (Green); Watershed Improvements |
| Hungry Ridge Restoration Project | Decision Signed Date: 03/24/2021 (FS Withdrawn) |
| Hungry Ridge Restoration SEIS | Decision Signed Date: 12/23/2024 |
| Forests | Nez Perce-Clearwater National Forest |
| Districts | Salmon River Ranger District |
| Legal Land Description | Not Applicable |