The Big Thompson Watershed Coalition and the Forest Service propose to use process based restoration techniques to improve water quality, protect downstream infrastructure, and promote channel resiliency within Elk Creek and its tributaries.
Location
The proposed project is located on Elk Creek which flows northeast into Buckhorn Creek along CR 44H before eventually entering the Big Thompson River.
Project timeline
1
Scoping Start
04/12/2024
2
Decision
05/2024 (Estimated)
3
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Canyon Lakes Ranger District |
| Legal Land Description | Not Applicable |