Structural calculations for the existing wood monopole at this facility have indicated that it needs to be replaced with a new tower that is structurally adequate for the necessary technology updates.
Location
Loveland Ski Area
Project timeline
1
Scoping Start
06/27/2025
2
Decision
04/2026 (Estimated)
3
Implementation
04/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Verizon Tower Replacement at Loveland Ski Area | Decision Signed Date: 04/13/2026 |
| Forests | Arapaho and Roosevelt National Forests |
| Districts | Clear Creek Ranger District |
| Legal Land Description | T4S, R76W, Sec. 28 |