Replacement of aerial powerline, realignments, and installation of buried powerline approximately 1.85 miles. Proponent is Powder River Energy Corporation.
Location
Thunder Basin National Grassland in Spring Creek Unit.
Project timeline
1
Scoping Start
10/21/2025
2
Decision
03/2026 (Estimated)
3
Implementation
03/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Duck Creek Powerline Relocation DGL514 Amendment no. 2 PRECorp | Decision Signed Date: 03/06/2026 |
| Forests | Medicine Bow-Routt National Forest |
| Districts | Douglas and Thunder Basin Ranger District |
| Legal Land Description | (Sec. 10, 11, 14 T. 55 N., R. 70 W.) Lot 9, S2SE, SESW Sec. 10; Lot 2, SW Sec. 11; Lot 14, E2NW, SWNE Sec. 14, T. 55 N., R. 70 W., 6th P.M. |