Remove old shelter building and separate tower; replace with new integrated shelter and tower. Minor hazard tree removal and brush removal.
Location
Pargin Mountain southeast of Bayfield, CO
Project timeline
1
Scoping Start
03/26/2019
2
Decision
04/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Decision Decided Date | 04/03/2019 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T34N R5W Section 14U |