Streambank stabilization, access improvement and improvement to aquatic habitat on the Dolores River
Location
Project locations south and east of the McPhee Reservoir and in the town of Dolores.
Project timeline
1
Scoping Start
07/01/2025
2
Decision
12/2025 (Estimated)
3
Implementation
12/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements |
| Fisheries - Dolores River Restoration Project | Decision Signed Date: 12/04/2025 |
| Forests | San Juan National Forest |
| Districts | Mancos/Dolores Ranger District |
| Legal Land Description | N1/2 of S. 16, T. 37N, R15W, N.M.P.M. SE1/4 of S. 5, T. 37N, R14W, N.M.P.M. N1/2 of S. 6, T 38N, R13W, N.M.P.M. |