Authorization for the installation and operation of a new buried 8-inch produced water pipeline, a new 6-inch produced water pipeline, and two co-located, up to 8-inch diameter low pressure natural gas pipelines in the West Mamm Creek area.
Location
Project is located south of Silt, Colorado in the West Mamm Creek drainage.
Project timeline
1
Scoping Start
08/11/2023
2
Comment Period
01/08/2025
3
Objection Period Start
03/19/2025
4
Decision
08/2025 (Estimated)
5
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390); Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| West Mamm Creek Pipeline Project | Decision Signed Date: 08/26/2025 |
| Forests | White River National Forest |
| Districts | West Zone/Rifle Ranger District |
| Legal Land Description | Sections 8, 9, 16, 21, 28 and 29. T7S, R93W, 6th PM. |