Reconstruction of the City of Flagstaff drinking water pipeline and the pipeline road (FR 146), at sites where it was washed out after the Schultz Fire. Some of the pipeline may be relocated to the Schultz Pass Rd (FR420) to avoid Wilderness.
Location
From Schultz Pass trailhead north to Windy Point on FR146
Project timeline
1
Scoping Start
04/04/2011
2
Decision
08/2011 (Estimated)
3
Implementation
08/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Maintenance |
| Inner Basin Waterline Reconstruction Project | Decision Signed Date: 08/17/2011 |
| Forests | Coconino National Forest |
| Districts | Flagstaff Ranger District |
| Legal Land Description | Intersection of Forest Road 146 and Forest Road 420 |