Project timeline

1
Scoping Start
06/21/2022
2
Decision
06/2022 (Estimated)
3
Implementation
07/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations; Watershed Improvements
Decision Decided Date06/30/2022
ForestsCoconino National Forest
DistrictsFlagstaff Ranger District
Legal Land DescriptionNot Applicable
Watershed managementSpecial use management