The Ridge Trail would be re-aligned because a portion is currently on private land. The Forest Service would construct the Ridge Trail realignment and adopt a user-created connector traveling from the Ridge Trail to the Ramshead Trail.
Location
West Sedona
Project timeline
1
Scoping Start
08/21/2024
2
Decision
09/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Ridge Trail Realignment | Decision Signed Date: 09/03/2025 |
| Forests | Coconino National Forest |
| Districts | Red Rock Ranger District |
| Legal Land Description | Not Applicable |