The Globe Ranger District proposes to extend an above ground pipeline from private land to a new storage tank and two new troughs on the Pinto Creek Allotment.
Location
The legal location of the project is Township 2 South, Range 14 East, Section 15.
Project timeline
1
Scoping Start
08/10/2022
2
Decision
03/2023 (Estimated)
3
Implementation
03/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Decision Memo Pinto Creek: Registered Pipeline | Decision Signed Date: 03/30/2023 |
| Forests | Tonto National Forest |
| Districts | Globe Ranger District |
| Legal Land Description | Not Applicable |