The purpose of this project is to approve the installation of fiber optic broadband infrastructure to the Roosevelt Lake Marina.
Location
The project is located at Roosevelt Lakeview Trailer Park and Roosevelt Lake Marina near the State Highway 188.
Project timeline
1
Scoping Start
04/02/2024
2
Decision
08/2025 (Estimated)
3
Implementation
11/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Tonto National Forest |
| Districts | Tonto Basin Ranger District |
| Legal Land Description | Not Applicable |