Categorical Exclusion Completed

Oaks Park Project

Ashley National Forest Uintah, Utah Ashley National Forest

This project is the replacement of two sections of the Oaks Park pipeline to maintain functioning water pipeline infrastructure in this area.

Location

The upper section of pipeline is below the Oaks Park Dam, accessed via Forest Service Road (FSR) 025 off the north end of the Red Cloud Loop. The lower section of pipeline is at Grasshopper Flat, west of FSR 044 (the Taylor Mountain Road). The project area is on the Vernal Ranger District in Uintah County, Utah.

Project timeline

1
NEPA Start Date
6/29/2026
2
Finding/Decision Date
7/8/2026

NEPA / regulatory detail

Categorical ExclusionUSDA-01d-FSA
Decision Signed Date7/8/2026
Special use management