The project proposes to install a wooden temporary fish barrier to remain in place for 2 - 3 years to aide in restoring native fish to Moody Creek.
Location
The location is along Moody Creek near Forest Service Road 403.
Project timeline
1
Scoping Start
04/22/2025
2
Decision
09/2025 (Estimated)
3
Implementation
09/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (25), 36 Cfr 220.6(E)(25) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Population Enhancements |
| Moody Creek Fish Barrier | Decision Signed Date: 09/03/2025 |
| Forests | Caribou-Targhee National Forest |
| Districts | Palisades Ranger District |
| Legal Land Description | Township 4N, Range 42E, Section 6 |