Environmental Assessment Completed

Alunite Ridge and North Fork Mineral Exploration

Fishlake National Forest Piute, Utah Beaver Ranger District

The Beaver Ranger District is conducting analysis of a mineral exploration project proposed by DT Mining, LLC near Alunite Ridge on the Tushar Mountain Range. Project activities include up to 18 drill pads and about 6 miles of road improvements.

Location

Project activities would take place near the Alunite Ridge and North Fork areas on the east side of the Tushar Mountain Range and approximately 6 miles southwest of Marysvale, Utah in Piute County.

Project timeline

1
Scoping Start
06/12/2024
2
Comment Period
06/12/2024
3
Objection Period Start
10/16/2024
4
Decision
12/2024 (Estimated)
5
Implementation
04/2025 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
Alunite Ridge and North Fork Mineral ExplorationDecision Signed Date: 12/12/2024
ForestsFishlake National Forest
DistrictsBeaver Ranger District
Legal Land DescriptionNot Applicable
Minerals and geology