Reconstruct the existind dam to address safety concerns related to age of the existing structure.
Location
Angel Lake
Project timeline
1
Scoping Start
04/24/2023
2
Comment Period
04/28/2023
3
Decision
03/2026 (Estimated)
4
Implementation
07/2026 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Maintenance; Watershed Improvements |
| Angel Lake Dam Stabilization | Decision Signed Date: 03/09/2026 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Ruby Mountains Ranger District |
| Legal Land Description | Not Applicable |