Re-routing of three road segments that are currently in drainage bottoms.
Location
Harrison Pass Area
Project timeline
1
Scoping Start
04/21/2023
2
Decision
05/2026 (Estimated)
3
Implementation
08/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Harrison Pass Area Road Re-route Project | Decision Signed Date: 05/28/2026 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Ruby Mountains Ranger District |
| Legal Land Description | Not Applicable |