Authorize the addition of a Fiber optic line to existing power poles along State Route 157, Telephone Pole Rd to Angel Peak communication site and along Cold Creek Rd. The planned installation will take place during calendar year 2025 if approved.
Location
Along St. Rt. 157 on existing power poles, to Angel Peak communication Site, and along Cold Creek Rd.
Project timeline
1
Scoping Start
08/15/2025
2
Decision
10/2025 (Estimated)
3
Implementation
04/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| VEA Fiber #194 Kyle, Angel, Cold Creek | Decision Signed Date: 10/29/2025 |
| Forests | Humboldt-Toiyabe National Forest |
| Districts | Spring Mountains National Recreation Area |
| Legal Land Description | Not Applicable |