The purpose is to issue a new Special Use Permit (SUP). The new SUP includes modifications to the existing facility including reductions in the amount of water diverted, changes to the point of diversion, removal of the dam, and restoration.
Location
T20N, R6E, Sections 28 and 29.
Project timeline
1
Scoping Start
04/07/2025
2
Decision
01/2026 (Estimated)
3
Implementation
05/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Watershed Improvements |
| Zena Creek Diversion Special Use Permit and Stream Restoration | Decision Signed Date: 01/23/2026 |
| Forests | Payette National Forest |
| Districts | Krassel Ranger District |
| Legal Land Description | Not Applicable |