The project would reroute less than one mile of Trail Creek-Cherry Creek Trail (FS Tr No 4347) to reduce the stream crossings. The proposed reroute would eliminate six of nine existing stream fords.
Location
Approximately 7 miles south of Mackay, ID
Project timeline
1
Scoping Start
05/06/2025
2
Comment Period
01/02/2026
3
Decision
03/2026 (Estimated)
4
Implementation
06/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements |
| Trail Creek-Cherry Creek Trail Reroute | Decision Signed Date: 03/12/2026 |
| Forests | Salmon-Challis National Forest |
| Districts | Lost River Ranger District |
| Legal Land Description | Not Applicable |