Project timeline

1
Scoping Start
03/24/2025
2
Decision
04/2026 (Estimated)
3
Implementation
08/2026 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other