The Sierra pacific Power Company (NV Energy) proposes replacing three transmission lines (101, 102, 133) to modernize the electric design line along the existing alignment (right of way) and improve reliability within the electric power grid.
Location
The project runs northeast from the west side of Donner Lake to Verdi, California following the existing 133 powerline rights of way.
Project timeline
1
Scoping Start
07/01/2024
2
Decision
04/2026 (Estimated)
3
Implementation
04/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Tahoe National Forest |
| Districts | Truckee Ranger District |
| Legal Land Description | Beginning at t17N, R15E, S17 running northeast to T19N, R18E, S7. |