There is a need to inoculate three seed orchards in late July/August to stimulate cone production. Available seed is an obstacle reforestation needs. Research has shown that this treatment may increase the production of cones.
Location
The ocrchards that will be treated include Lost Creek (Klamath), Horsehoe (Lakeview), and Hager (Silver Lake).
Project timeline
1
Scoping Start
05/11/2023
2
Decision
06/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.11, 7 Cfr 1B.3(A) (3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| Decision Decided Date | 06/15/2023 |
| Forests | Fremont-Winema National Forest |
| Districts | Klamath Ranger District |
| Legal Land Description | T.36S., R.6E., Sec.7, T.40S., R.18E., Sec. 22, T. 30., R. 14., Sec. 4. |