Replace existing septic field lines for the YACC House at the Open Pond Work Center an Administrative Site.
Location
South of County Road 24 and west of Tower Road at the Open Pond Workcenter administrative facility.
Project timeline
1
Scoping Start
02/16/2024
2
Decision
04/2024 (Estimated)
3
Implementation
03/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Maintenance |
| Decision Decided Date | 04/15/2024 |
| Forests | National Forests in Alabama |
| Districts | Conecuh Ranger District |
| Legal Land Description | Not Applicable |