This project will restore the headwaters of Perry Creek by improving aquatic habitat connectivity and hydrologic function, while allowing National Forest System lands to be more resilient in future storm events. The removal of a private dam and restoring the stream to it's flood plain are proposed.
Location
FSR 151 (Mooneyham Road)
Project timeline
1
NEPA Start Date
12/16/2025
2
Finding/Decision Date
8/27/2026
NEPA / regulatory detail
| Categorical Exclusion | USDA-40d-USFS; USDA-41d-USFS |
| Decision Signed Date | 8/27/2026 |