Decision Memo Completed

Max Patch Improvement Project

Cherokee National Forest Cocke, Tennessee Unaka Ranger District

Replace the existing kiosk with a 3-panel kiosk and construct a 200 foot split rail fence that will start about 25 feet behind the kiosk.

Location

Max Patch

Project timeline

1
Scoping Start
07/27/2018
2
Decision
11/2018 (Estimated)
3
Implementation
09/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
Decision Decided Date11/01/2018
ForestsCherokee National Forest
DistrictsUnaka Ranger District
Legal Land DescriptionNot Applicable
Recreation management