Project timeline
1
Scoping Start
06/09/2014
2
Decision
09/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.3 (3) |
| Special Authority | Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390) |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Oil |
| Decision Decided Date | 09/22/2014 |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Sec. 20, T2N, R10W, St. Stephens Meridian |