Categorical Exclusion Completed

Weston Powerline Installation Project

Ouachita National Forest Montgomery, Arkansas Womble Ranger District

Entergy Arkansas, LLC is requesting the authorization of installing approximately 1,200 feet of single phase, 7,200 volt, aerial power distribution line to proivde electric service to private property.

Location

8 miles northwest of Meyers

Project timeline

1
NEPA Start Date
7/17/2026
2
Finding/Decision Date
9/10/2026

NEPA / regulatory detail

Categorical ExclusionUSDA-28d-USFS
Decision Signed Date9/10/2026
Special use management