Treatments would occur on .25-mile of the trail (from bridge to overlook) and include removing some vegetation and all deteriorating structures. The new access route will be built and maintained to look and appear natural to the area.
Location
The project area is located 3.46 miles northwest of the community of Albert Pike.
Project timeline
1
Scoping Start
04/25/2025
2
Decision
06/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | Ouachita National Forest |
| Districts | Caddo Ranger District |
| Legal Land Description | Not Applicable |