Proposal to combine and re-issue three Special Use Permits for approximately 25.75 miles of already existing powerlines to Mid-South Synergy. The lines provide service to multiple private land inholdings in several compartments and two counties.
Location
Compartments 4-6, 11, 14, 15, 17, 30, 31, 33, 35-38, 44-47, 49-51
Project timeline
1
Scoping Start
08/30/2012
2
Decision
02/2014 (Estimated)
3
Implementation
02/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | National Forests In Texas |
| Districts | Sam Houston Ranger District |