Environmental Assessment Completed

Forest Road 164 Reconstruction

Chequamegon-Nicolet National Forest Ashland, Wisconsin Great Divide Ranger District

The 11.6-mile-long project area will be cleared and grubbed within 16 feet of the road centerline or as needed to create ditching. All cross-drain culverts will be replaced with polymer coated arch pipes. The entire road length will be resurfaced.

Location

Forest Road 164 between County Highway GG and Forest Road 163.

Project timeline

1
Scoping Start
01/31/2022
2
Comment Period
08/28/2025
3
Objection Period Start
08/28/2025
4
Decision
10/2025 (Estimated)
5
Implementation
11/2025 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Maintenance; Road Improvements/Construction; Travel Management
Forest Road 164 ReconstructionDecision Signed Date: 10/22/2025
ForestsChequamegon / Nicolet National Forest
DistrictsGreat Divide Ranger District
Legal Land DescriptionNot Applicable
Road management