Request from the Town of Alvin to widen FS road 2458 by stumping and grubbing in areas where the road prism is less than 18 feet wide.
Location
FS Rd 2458 (Carey Dam Rd) road prism and right of way
Project timeline
1
Scoping Start
01/22/2026
2
Decision
01/2026 (Estimated)
3
Implementation
02/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (23), 36 Cfr 220.6(E)(23) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| 2024 Town of Alvin ROW FS Road 2458 Stumping/Road Widening | Decision Signed Date: 01/22/2026 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | Not Applicable |