Wisconsin Electric Power Company (WE) is proposing to rebuild their existing powerline which would consist of overhead removal and restoration, and underground relocation. The proposed removal and installation are proposed on approximately 17 acres.
Location
State Highway 55 and County Trunk Highway A in Forest County
Project timeline
1
Scoping Start
05/08/2025
2
Decision
09/2025 (Estimated)
3
Implementation
10/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 2025 Wisconsin Energy Rebuild Project | Decision Signed Date: 09/03/2025 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | T40N R13E Section 2; T41N R13E Section 13,16,17,20, 21, 24, 25, 26 & 36 |